This was our first dome. It was built for Jason and Amanda Slick in McMahan, TX. Thank you to Travis Lott for lots of hard work on this. Also thanks to Jesse Garrett for helping out. Amanda also did her fair share. Jason did a whole lot of work on this dome, doing most of the finishing himself. The dome was built between December 2008 and February 2009.
Prepared the footing form

The ready mix truck has arrived

pouring the footing

Screeding the slab

Inserting the rebar that ties the footing to the shell

Keyway (to join the footing to the shell well)

rebars bent down to prepare for airform

Inside the dome (just the airform)

polyurethane has been sprayed and these are rebar hangers

second layer of concrete covering the rebar

last coat of concrete

the bathroom shower

the toilet

view toward the door

kitchenette

Mima's cozy bed.

Welcome home!